Which Post-Tensioning Tendon?

29 Apr.,2024

 

Which Post-Tensioning Tendon?

Which End to Stress First?

In post-tensioned floors, tendons are stressed after cast concrete gains adequate strength. The stressing operation is monitored to ensure that tendons receive their design-intended force.

If you want to learn more, please visit our website Ruiyi.

Three questions on tendon stressing are often raised among post-tensioning crews. These are:

  1. What is the right sequence of tendon stressing when the structure has multiple tendons with different arrangements, such as common two-way slab systems.?
  2. When long tendons are marked for stressing at both ends, which end should be stressed first and what is the right order for correct elongation measurement?
  3. How are the stressing records reconciled when the elongation measurements are outside the target limits?

This article covers the first two questions. A follow-up article will address the third.

Stressing Sequence

When there is more than one tendon or one tendon group in the construction, one question is – which tendon group to stress first?

The following text is from the General Notes of a typical construction document for post-tensioned floors.

The general tendon stressing sequence for one-way systems shall be as follows:
First: uniformly distributed tendons;
Second: beam tendons;
Third: girder tendons.

The General tendon stressing sequence for two-way systems shall be as follows:
First: uniformly distributed tendons;
Second: banded tendons.

Continuous tendons in multi-span beams (girders) shall be stressed before any non-continuous tendons.

To fully appreciate the significance of the above instructions and their applicability, two considerations are important.

First, in standard construction, the entire floor is resting on forms at the time of stressing. Post-tensioning results in bending stresses in the slab or beam only if the uplift from the post-tensioning tendons is greater than the self-weight of the member being stressed. Bending stresses result from a change in the curvature of the member. If the member being stressed remains in contact with its support, its curvature does not change – hence no bending stresses (Figure 1).

Figure 1. Post-tensioned member at stressing.

Second, in standard building construction, post-tensioning for slabs or beams is typically selected to provide uplift between 60% to 80% of the member self-weight, or, in the case of beams, the self-weight of the beam and the reaction from members that shed load on the beam. Again, if, at stressing, the post-tensioning is not large enough to lift the members that load the beams, the distribution of load among the members’ envisaged in-service conditions does not occur.

The following illustrates that, for common conditions, standard design parameters do not favor a specific stressing sequence.

Beam and One-Way Slab Construction

Figure 2 shows a post-tensioned beam and one-way slab construction. The slab and beam tendons are each profiled to counteract their respective self-weights.

Apart from its own weight, the beam carries the reaction from the slab it supports. The question on stressing sequence reduces to the following: Does stressing of the slab before or after beam stressing impact the beam’s performance either during the construction or when in service?

Figure 2. Post-tensioned beam and slab construction; single and multi-span slabs.

For the single-span slab shown in Figure 2a, the slab reaction on the beam does not depend on whether or not the slab is stressed and how much of the slab weight is balanced by post-tensioning. The slab reactions, as shown in Figure 3, remain unchanged. The load on the beam is independent of the state of stressing in the slab. For this reason, it is immaterial whether the beam or the slab is stressed first. Likewise, the stressing of the beam does not impact the response of the slab. The sequence of stressing can be based on the expediency of construction. The other consideration is that the beams are rarely designed to provide uplift beyond their own weight and the reaction of the slabs they support. The beam is not likely to lift off its support when stressed first.

Figure 3. Reactions of a single-span member.

Figure 2b shows a multi-span member, such as slabs over parallel beams. In this case, the slab reactions on the beam depend on whether the slab tendons are stressed or not – tendon stressing changes each of the reactions from gravity by the hyperstatic forces from prestressing. The question is whether the change in the slab reaction on the beam arising from slab stressing is large enough to impact the beams’ response.

Referring to Figure 2b, where the slab spans over several beams, the load on the beams will be different depending on whether the slab is stressed. In this case, in principle, the sequence of stressing matters. But, since the hyperstatic reactions from prestressing are generally much smaller than the reactions from self-weight, the sequence of stressing is not viewed as consequential. Again, the question is addressed since, at stressing, the slab and beam are both supported.

In summary, for either single or multi-span beam and slab construction, the sequence of stressing may be based on the convenience of construction. Each member may be stressed in full before moving to the next.

Two-Way Slab Construction

There are several options in the tendon layout of two-way slabs. Figure 4 is a partial view of a two-way slab illustrating the typical banded-distributed layout of tendons.

Figure 4. Partial view of slab showing the banded-distributed layout of tendons.

Two questions arise in connection with the sequence of stressing: first, whether the sequence of stressing will result in local over-stress at construction. Second, whether the sequence will change the resulting load-carrying characteristic of the floor system when in service.

In practically all constructions, the post-tensioning is fine-tuned to balance a fraction of the member’s self-weight, typically 50% to 80% – not more than the member’s total weight at stressing. Hence, the slab will not lift off the form support. Extreme fiber bending stresses will form only if stressing results in a change in slab curvature.

The common practice is that distributed tendons are stressed first. As an example, for the condition shown in Figure 4 with interior spans at 29 feet and slab depth at 7.5 inches, the uplift from the post-tensioning of banded tendons must exceed 80% of the slab’s self-weight before the slab partially lifts off the form. The sequence of stressing is not critical to the stress condition of the slab either at stressing or when in service. The convenience of construction favors stressing sequence.

Stressing Sequence

When a long tendon is marked to be stressed at both ends, the following questions arise.

(i) Which end should be stressed first?
(ii) Should one end be stressed to full value and seated before stressing the other end? Or, should one end be partially stressed, be seated, and the second end stressed to completion?
(iii) Should both ends be stressed simultaneously?

Briefly, at stressing, the jack pulls the prestressing strand out of the anchor piece. Once the jacking force reaches the design value, the strand is anchored at the face of the member. The common anchoring mechanism is by way of wedges that grip the strand. The retraction of the wedges into the conical cavity of the anchorage grips to lock the pulled strand into position.

In Post-Tensioned Buildings: Design and Construction (2014), the author provides the details of the stress loss in the tendon and other considerations that govern the force in the tendon at stressing and long-term effects. The focus of the following is a sequence of stressing and measurement of tendon elongation.

Figure 5. Force diagram of a two-end stressed tendon.

Figure 5a shows a post-tensioned member to be stressed at both ends. The common practice is to stress one end to its design force, seat it, stress the second end to its design force, and seat the second end. Tendons are simultaneously stressed at both ends only in special circumstances. The common practice is to stress the tendon ends to full force, one end after the other.

Under full force at the left end, the distribution of force in the tendon is shown by line AB (Figure 5b). The distribution is shown by a straight line to explain the concept. The force drop along the tendon length is governed by the tendon’s geometry and the tendon’s other properties. It is close to a straight line.

Point A marks the tendon force at maximum jacking pressure. Once seated, the retraction of the wedges into the anchor cavity results in some stress loss. Once fully seated, the tendon force diagram is shown by line DCB. ACD is the stress loss from the retraction of the wedges.

The extension length of the strand after it is seated is proportional to the area below the curve DCB. The larger the area, the longer is the extended length of strand protruding out of the anchor block. The extended length beyond the anchor block is referred to as tendon “elongation.”

The direct correlation between the force in the tendon, given by the area below the force diagram, and the elongation of the strand, evidenced by its extended length out of the member, is used to verify the successful jacking operation. For successful stressing, the tendon elongation is matched against the area below the stressing curve (Figure 5b).

Figure 5c shows the force diagram after stressing and seating of the second end. BEFH marks the change in the tendon’s force diagram resulting from stressing and seating of the second end.

The extension length of the strand after stressing of the second end is proportional to the area BEFH. Comparing the area below the force diagram associated with the stressing of the first end and that of the second end, it is evident that the elongation of the tendon at the second end is less than that of the first end.

The final force diagram of the tendon, when stressed in full and seated, is shown in Figure 5d. Irrespective of the stressing sequence, if during the stressing operation, at some point and each end, the tendon is pulled to the design force (points A and G), the final force diagram will be DCEFH. And the sum of the elongations of the two ends will be proportional to the area below DCEFH.

From the preceding, the successful stressing operation of the tendon is measured by matching the sum of the elongations at the two ends against the calculated value based on the area below the diagram DCEFH.

In summary, the sequence of stressing a tendon (or whether the stress at one end is applied partially and followed by stress at the other end before completing the stress at the first end) does not impact the total elongation and the force distribution in the tendon. This is on the premise that the stressing operation is concluded when each end, at some point, has been stressed to the full value.■

Reference

Aalami, B. O. (2014). Post-Tensioned Buildings; Design and Construction, Book; www.PT-Structures.com; pp. 450.

Post-Tension Slab Analysis & Design

(Click the table of contents to navigate to the detailed content)

 

Post-Tension Slab Analysis & Design


Please fill out the Download Section (Click here) below the Comment Section to download the Structural Design Guide for Prestressed Slabs.

 

 

 

Table of Contents 

 

What is Post-Tensioning?

 

 

 

 

 

Post-tensioning is a technique for reinforcing concrete. Post-tensioning tendons, which are prestressing steel cables inside plastic ducts or sleeves, are positioned in the forms before the concrete is placed. Afterward, once the concrete has gained strength but before the service loads are applied, the cables are pulled tight, or tensioned, and anchored against the outer edges of the concrete.

 

Post-tensioning is a form of prestressing. Prestressing simply means that the steel is stressed (pulled or tensioned) before the concrete has to support the service loads. Most precast, prestressed concrete is actually pre-tensioned-the steel is pulled before the concrete is poured. Post-tensioned concrete means that the concrete is poured and then the tension is applied-but it is still stressed before the loads are applied so it is still prestressed.

 

Advantages & Applications of Post-Tensioning

 

 

 

                  * It reduces or eliminates shrinkage cracking-therefore no joints, or fewer joints, are needed.
                 * Cracks that do form are held tightly together.
                 * It allows slabs and other structural members to be thinner.
                 * It allows us to build slabs on expansive or soft soils.
                 * It lets us design longer spans in elevated members, like floors or beam.

 

 

 

Post-Tension Type

 

 

(a) Bonded Post-Tensioning
It is used for large structural elements such as beams and transfer girders, design advantages include increased span lengths and load carrying capacity and reduced deflection.

 

(b) Unbonded Post-Tensioning
It is typically used in new construction for elevated slabs, slabs-on-grade, beams, and transfer girders, joists, shear walls, and mat foundations. Light and flexible, the unbonded mono strand can be easily and rapidly installed – providing an economical solution.

 

 

Strength of Prestressing Steel

 

 

 

 

Figure 1: Wheel load dispersion; hc < 2 ft) - Source: AASHTO LRFD

 

 

Step Immediately after prestressing After anchoring Tension Stress Min[ 0.94 fpy, 0.80 fpu ] 0.70 fpu  


 

Diameter Aps

(mm2)

fpu (Mpa) fpy (Mpa) fpe (Mpa) Fst (kN) Fse (kN)

12.7mm

98.71 1,860 1,674 1,200 146 118.4 15.2mm 138.7 1,860 1,674 1,200 205 166.4

 

 

Aps : Area of prestressing steel

fps : Stress in prestressed reinforcement at nominal strength
fpu : Specified tensile strength of prestressing steel
fpy : Specified yielding strength of prestressing steel (0.90* fpu= 0.90*1,860Mpa = 1,674Mpa)
fpi : Initial prestress stress of prestressing steel
fpe : Effective prestress stress of prestressing steel (0.65* fpu= 0.65*1,860Mpa = 1,200Mpa)
Fst : Max. prestress force ( Min[ 0.94 fpy, 0.8 fpu ] *Aps = Min[ 1,573 or 1,485 ] *138.7 = 205kN )
Fse : Effective prestress force ( fpe*Aps = 1,200Mpa*138.7 = 166.4kN )
Fps : Ultimate prestress force

 

 

Design Steps

 

 

 

Figure 3: Wheel load dispersion (Overlapping dispersion area); hc > 2 ft - Source: AASHTO LRFD

 

         (a) Post-tensioned member                                               (b) Tendon removed

                                                                                                                                 Step 1: Jacking Stage (Fst)

                                                                                                                                 Step 2: Transfer Stage (Fpi)

 

 

 

 

                                        (c) Service condition (SLS)                                                  (d) Strength condition  (ULS)

                                           Step 3: Service Stage (Fse)                                                     Step 4: Ultimate Stage (Fps)

 

 

After Jacking Stage

• Activity of anchorage device
• Tension force loss due to friction
• Tension loss due to elastic shrinkage of concrete

 

AfterTransfer Stage
• Tension loss due to creep
• Tension loss due to shrinkage
• Tension loss due to strand relaxation

 

 

Loading Conditions

 

 

 

Transfer Stage

• Using Prestress Force → Fsi (before short/long-term tension loss occurs, Max. prestress)
• Using Concrete strength : fci (compressive strength of concrete when prestress is introduced, Min. strength)
• Loading : only Self-weight (before adding a finishing and live loads)
• Checking item : Tensile cracking and crushing of concrete, failure of anchorage part.

The company is the world’s best post tensioning system services supplier. We are your one-stop shop for all needs. Our staff are highly-specialized and will help you find the product you need.

 

Service Stage

• Using Prestress Force  → Fse (Effective tension after short/long-term tension loss occurs)
• Using Concrete strength : fck (Max. design strength)
• Loading : All design load (Unfactored Load)
• Checking item : Deflection, Crack Width.

 

Ultimate Stage

• Using Prestress Force → Nominal Strength
• Using Concrete strength : fck (Max. design strength)
• Loading : All design load (Factored loads)
• Checking item : Flexural failure or compression stress under flexural behavior.

 

 

 

Definition of Member Forces

 

 

Example 1: Continuous Beam

 

MS : Moment due to own weight of concrete section.
MO : Moment due to other applied loads.

M1 : Primary moment → Moment by the distance between the section center and the prestressing point.

In example 1: M = Prestressing force x Eccentricity distance = P x -e = -Pe

Δ : Deflection by M1 →Deflection at point B when considered as a simple beam.

In example 1 : "Δ"=(Mol2 )∕8EI= (Pe(2l)2 )∕8EI=(Pel2 )∕2EI

R : Reaction by Δ → Point B should not be deflected by the support, so a reaction force is generated so that deformation as much as (-)Δ occurs.

 

In example 1 :  

 

MSecondary : Secondary Moment → Moment caused by R
* MSecondary means the moment created by the reaction force that restrains the deformation caused by M1.

In example 1 :  𝑀𝑆𝑒𝑐𝑜𝑛𝑑𝑎𝑟𝑦 𝑎𝑡 𝑝𝑜𝑖𝑛𝑡 𝐵=(3𝑃𝑒/2𝑙)×𝑙=3𝑃𝑒/2

MNet : Net final Moment = M1 + MSecondary : Moment acting on the actual continuous beam by prestressing.

In example 1 : 𝑀u 𝑎𝑡 𝑝𝑜𝑖𝑛𝑡 𝐵=−𝑃𝑒+(3𝑃𝑒/2)=𝑃𝑒/2

 

 

Thickness or Depth of Section

 

<Thickness-span correlation by each slab system>

 

• RC Member

Span/Depth

Continuous span

Simple span

Beam

21

16

2-way slab

30

-

1-way slab

28

20

 

 

• Post Tension Member

Span/Depth Continuous span Simple span Roof Not Roof Roof Not Roof Beam 60% 70% 53% 62% 2-way slab 63% 71% - - 1-way slab 56% 62% 44% 50%

 

 

• Reduction ratio of thickness or depth when PT is applied

RC/PT (%)

Continuous Span

Simple span

Roof

Not Roof

Roof 

Not Roof

Beam

60%

70%

53%

62%

2-way slab

63%

71%

-

-

1-way slab

56%

62%

44%

50%

 

 

The thickness is reduced by 30-50% compared to the RC member. Alternatively, an economical design can be made by reducing the amount of rebar or tendon required for the same thickness.

 

 

 

Post-Tension Slab Procedure

 

Step 01 : Installing slab formwork

Step 02 : Installing slab rebar

 

Step 03 : Placing bar chair by profile height

 

Step 04 : Placing tendon on the bar chair

Step 05 : Add extra rebar

Step 06 : Pouring concrete

Step 07 : Insert block and jaws bar chair

Step 08 : Stressing and measuring elongation

Step 09 : Grouting

 

 

 

Design Flow Chart for Post-Tension

 

 

 

1. Choose Tendon force and profile

Tendon Profile Type

How to arrange tendon of parabolic shape

 

 

After Transfer Stage

 

 

2. Check final stresses and Check initial stresses

 

Allowable stress for Concrete                                                                                                                                         unit : (MPa)

Checking Stage Conditions Allowable stress under Initial Service Load (Initial) 1. Extreme fiber stress in compression pci = 0.60 fci 2. Extreme fiber stress in tension pti = 0.25 fci0.5 3. Extreme fiber stress in tension at ends of simply supported members pti = 0.50 fci0.5 under Service Load (Final) 1. Extreme fiber stress in compression (at Long-Term Service Load) pcf = 0.45 fck 2. Extreme fiber stress in compression (prestress + total load) pcf = 0.60 fck 3. Extreme fiber stress in tension ptf = 0.50 fck0.5

 

Allowable stress for Tendon (Strand)                                                                                                                          unit : (MPa)

Checking Stage Conditions Allowable stress During Stressing - Max [0.94 fpy, 0.8fpu] Immediately after stressing - 0.70fpu

 

Please download the white paper of Structural Design Guide for Prestressed Slabs below to see the full contents. 

 

Are you interested in learning more about wholesale post tension wedges? Contact us today to secure an expert consultation!